The partially completed inventory record for the drive shaft subassembly in the table below shows gross requirements, scheduled receipts, lead time, and current on-hand inventory.
a. Complete the last three rows of the record for an FOQ of 60 units. (Enter your responses as integers. A response of “0” is equivalent to being not applicable.)
Item: Driveshaft subassembly Lot Size:
Save your time - order a paper!
Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines
Order Paper NowFOQequals=60 units
Lead Time: 3 weeks
Week
1
2
3
4
5
6
7
8 Gross
requirements
30
25
20
25
45
45
40
40 Scheduled
receipts
75 Projected on-hand
inventory
15 Planned
receipts